1、During the first half of the project. five team members left for other projects without being replaced. two team members went on vacation wIThout informing you. and other tEAMmembers expressed uncertainty about the work they were to complete. In this situation.ITis BEST if you create a _____for the second half of the project.
A. work breakdown structure
B. resource histogram
C. staffing management plan
D. responsibilITy matrix
1、在項目的前半段,有5個項目組成員離開到其它的項目去,而沒有資源來替代。2個項目組成員在沒有通知你的情況下去休假。其它的項目組成員對是否能夠完成自己的工作表示懷疑。在這種情況下,你為項目後半段創建______是最合適的?
A. WBS。
B. 資源柱狀圖。
C. 人員配備管理計劃。
D. 責任矩陣。
答案:C. 人員配備管理計劃。
分析:人員配備管理計劃描述了資源何時獲取和如何離開。
A. monITors and controls the project’s schedules, costs, scope, budgets, etc.
B. is a mechanism which reacts to the current project status in or
..............................